By Dr. Albert Ponsteen

Stopping a project takes courage. It also takes information, and that is the harder part. A project cancellation is the right decision when the whole portfolio earns more without the project than with it, after the cost of stopping has been counted. No status report tells you that. This article puts a number on each of the nine excuses for carrying on, from what the next dollar brings in to what a week of not deciding costs.

I wrote the nine excuses down in Nine Lame Excuses for Not Killing Projects on Flow Economics, each with what to do instead. When I asked on LinkedIn which one people hear most, many answers were about something else: how hard the decision is. One reader had watched a program use people for 18 months after everybody had stopped believing in it, because nobody wanted to be the one who called it. Another wrote that no forum has the explicit job of stopping a project.

They are right. Now suppose the courage is there. Which project do you stop, and on what information? That information is not simple, and most of it is in no report. The numbers below are worked out on three projects at a machine builder. A number does not take the decision for you. However, once an excuse has a price you can weigh it against the alternatives, and the courage comes a lot easier. The nine are suggestions and not the last word. Every business will weigh them differently, and at the end I ask which number you would add.

Excuse bingo card: nine numbers you need before you kill a project, one for each excuse for carrying on. 1 "We have already spent so much on it": what the next dollar brings in. 2 "We are almost there": what finishing still costs. 3 "We cannot say no to this customer": what saying no really costs. 4 "We must get something to market": what a week of delay costs. 5 "It is the CEO's project": what it costs the other projects. 6 "We have nothing better to work on": what the same hours earn elsewhere. 7 "Nobody has the whole picture": what the portfolio earns without it. 8 "We have no way to stop a project": the limit agreed in advance. 9 "It is just hard to say no": what a week of not deciding costs. A good decision takes the full card. Every excuse has a price; ask for it.

Nine excuses, and the number we ask for with each. Which number are you missing?

A machine builder, three projects

A machine builder runs three projects, A, B and C, and all three wait for the same five engineers. Engineering is the bottleneck, i.e., the people and skills that every project waits for. Figure 1 shows the three projects as they stand today: what each still brings in, what it still costs, how many hours of engineering it needs, and what a week of delay costs it. That last price is there whatever causes the delay, a queue at engineering or a late supplier. It can be a penalty for late delivery, or recurring revenue that cannot start.

Three projects, one engineering team. Engineering: five people, 200 hours a week, 2,600 hours this quarter, $100 an hour on average. Three cards. Project A: revenue at approval $1,500,000, still to collect $1,500,000, still to spend $150,000, hours of engineering 1,000, a week of delay costs $20,000. Project B: revenue at approval $1,125,000, still to collect $1,125,000, still to spend $225,000, hours of engineering 1,500, a week of delay costs $10,000; B is at twice its original budget. Project C, the project we follow: revenue at approval $1,250,000, still to collect $180,000, still to spend $150,000, hours of engineering 1,000, a week of delay costs $4,000; C is two quarters late.

Figure 1. The three projects as they stand today, and the team they wait for.

We follow project C. It was approved as a good project, it ran late, and the delay cost it most of its revenue. Today it is the one people argue about.

The excuse bingo card holds nine numbers, one for each excuse. They answer three questions, and this article follows them: what the project is worth on its own, what it does to the other projects, and what the portfolio earns with it or without it. Where an excuse comes up, its item on the card is given in brackets.

1. The project on its own: what does carrying on bring in, and what does stopping cost?

On paper C was a good project: two and a half dollars back for every dollar. Then it ran two quarters late, the launch customer cut its order, and a competitor got there first. This is where the first two excuses on the bingo card come in, and they come together: we have already spent so much on it (item 1), and we are almost there (item 2). Both look back at sunk cost. What has been spent is gone whatever you decide, and the work that is done is done. So look only at what is left. The next dollar you put into C comes back as a dollar and twenty cents. That is not an investment, that is treading water.

Project C: at approval, and today. What has been spent is gone; what counts is what is still to come. Left card, at approval: budget $500,000, revenue $1,250,000, ROI 2.5x, $2.50 back for every dollar. Right card, today: spent and gone whatever you decide $600,000; still to spend $150,000, of which $50,000 is direct cost that stops if you stop and $100,000 is own people who stay on the payroll; still to collect $180,000; RRI, return on remaining investment, 1.2x, $1.20 back for every dollar still to spend, minus $4,000 for every week it finishes later. Project B, for comparison: twice its budget, and $5.00 back for every dollar still to spend.

Figure 2. Project C at approval and today. What has been spent is gone; what counts is what is still to come.

We call this number RRI, the Return on Remaining Investment: what a project still returns for every dollar left to spend, shown as a multiple. ROI looks at the whole investment. RRI looks only at what is still to come. It is Epicflow's implementation of Stephen Devaux's Index of Project Performance (DIPP) [1]. The same number saves project B. B is far over its budget, and every dollar it still needs comes back five times. Money already spent is no reason to carry on with C. It is no reason to stop B either.

"Almost there" also hides what finishing really costs. Of what is still to be spent, only a third is direct cost that stops on the day you stop: materials, a subcontractor. The rest is the time of your own people, and that is operating expense. They stay on the payroll whatever you decide. So the budget that stopping saves is smaller than the report says, and what stopping really frees is their hours.

Item 3 on the bingo card, we cannot say no to this customer, is a different matter, and at a dollar twenty it is a fair one. C earns little, but what does a no cost? The revenue that goes, less the direct cost that stops; the penalty in the contract; and the part that is not in money at all, the customer you want to keep. Not every piece of that has a number, but the pieces that do are now on the table, and you can weigh the rest against them. And there is a third answer besides yes and no: later. A later date costs a project its weekly price of delay, and for C that price is small. A customer who cannot hear a no can often hear a date.

So looked at on its own, C should carry on. Stephen Devaux made the same point about sunk cost in the discussion on LinkedIn: a project can lose most of its expected value and still be worth finishing, as long as what it still costs falls with it. He also named what the figures of one project leave out, among them opportunity cost and resource bottlenecks. That is the second question.

What to look at in your planning system: for every project, the revenue as it stands today and not as it was approved; the cost still to come, split into direct cost that stops with the project and operating expense that stays; the hours still needed per resource group; and the delay cost per week (a bonus or penalty, revenue that starts later).

2. What it does to the other projects: what do the same hours earn elsewhere?

So far we have looked at C on its own. But C does not run on its own. All three projects need the engineering team, and engineering is the bottleneck: every project waits for it, and an hour it spends on one project is an hour the other two do not get. C still needs 1,000 of its hours, five weeks of the whole team.

C is also the CEO's pet project (excuse bingo item 5), so it goes to the front of the queue and the other two wait for the bottleneck. Figure 3 shows what that costs. A and B finish five weeks later, and every week of that has a price. Every project must get something to market (excuse bingo item 4), and the price of a week of delay is what makes that pressure comparable between projects. Behind C, the other two lose $150,000.

Five weeks behind C: what the other projects pay when C goes first. Delay cost per week: A $20,000, B $10,000, C $4,000. Both plans finish all three projects; only the waiting differs. Plan C first: C in weeks 0 to 5, A in weeks 5 to 10 (five weeks later, delay cost $100,000), B in weeks 10 to 17.5 (five weeks later, delay cost $50,000); total delay cost $150,000. Plan C last: A in weeks 0 to 5, B in weeks 5 to 12.5, C in weeks 12.5 to 17.5 (12.5 weeks later, delay cost $50,000); total delay cost $50,000.

Figure 3. What the other projects pay when C goes first. Both plans finish all three; only the waiting differs.

Nobody has budgeted for that amount. It is not in C's business case, and not in A's or B's either (the ledger is asymmetric). It arrives months later, as two other projects that are late, and by then nobody connects it to C. Somebody gets the blame for the delay cost all the same. If C waits, it is C's project manager; if C goes first, it is the project managers of A and B. None of them could do anything about it. Who waits for the bottleneck is decided above them, and that makes the delay cost a management decision, not a project problem.

A project nobody stops is paid for by the projects you meant to finish.

Nothing better to work on, people say, and that is item 6 on the bingo card. Take that seriously, because when it is true it settles the matter. Stopping C does not lower the payroll; the first chapter showed that the only thing stopping really frees is the engineers' hours. If those hours would otherwise sit idle, finishing C costs the company no more than its direct cost, and C brings in more than that. The excuse fails only when there is better work for the hours. So the question is how to tell better work from worse.

Eliyahu Goldratt taught us where to look, with what is now called throughput accounting. A project's throughput is what it brings in, less the direct cost that goes with it. Profit is throughput minus operating expense, and operating expense hardly moves within a quarter, so profit moves with throughput. And how much throughput a company can generate in a quarter is set by its bottleneck: every hour of engineering can go into one project only. So the measure of better work is throughput per hour of the bottleneck. Take what each project still brings in, after the direct cost that stops with it, and divide it by the hours it needs from engineering. This is RRI over the hours of the bottleneck: the return on the remaining hours instead of the remaining dollars. No hourly rate tells you this; only the alternatives do.

Figure 4 shows the result. The same hour of engineering earns more than ten times as much on A as on C.

Throughput per hour of the bottleneck, after Goldratt's throughput accounting: what each project still brings in, after the direct cost that stops with it, for every hour of engineering. Project A $1,450 an hour, project B $700, project C $130. The portfolio average is about $750 an hour. A earns more than ten times what C earns from the same hour of engineering.

Figure 4. Throughput per hour of engineering: what each project still brings in, after the direct cost that stops with it, for every hour of the bottleneck.

So is there better work? A and B on their own can keep engineering busy for the whole quarter, so every hour that goes to C comes out of theirs. No new project is needed for that. "Nothing better" is rarely true, and now you can check it.

What to look at in your planning system: one plan for all projects on the same capacity, so that giving one project its hours first shows the new finish dates of the others; which resource group is the bottleneck, how many of its hours every project still needs and what each project still brings in after direct cost, so you can rank them by throughput per hour of the bottleneck; and the delay cost per week of every project, not only of the one that shouts loudest.

3. The portfolio, and the decision: what does it earn with C kept first, pushed back or taken out?

And now we come to item 7 on the bingo card: nobody has the whole picture. True, until somebody draws it. There are three things you can do with C: keep it at the front of the queue, where it is today; push it back; or take it out. Each of them moves the other projects. So calculate the whole portfolio for each, and put a fourth plan next to them: what happens if nobody decides. In the first two chapters the whole team worked on one project at a time. In practice, when nobody decides, that is not what happens. Engineering capacity is spread over the three projects, every engineer is assigned a percentage to each, so that every project is served and nobody is told to wait. Figure 5 puts all four plans on one timeline, and this is what it looks like.

Four plans for the same engineers: when each project is finished, and the quarterly revenue, with the end of the quarter at week 13. Nobody decides: engineering is spread over all three projects, A, B and C all finish after 17.5 weeks, quarterly revenue $0. Today, C first: C finishes in week 5, A in week 10, B in week 17.5, quarterly revenue $1,680,000. Push C back: A finishes in week 5, B in week 12.5, C in week 17.5, quarterly revenue $2,625,000. Take C out: A in week 5, B in week 12.5, 1,000 hours of engineering free, quarterly revenue $2,625,000. Every week without a decision costs the portfolio about $17,000.

Figure 5. The four plans on one timeline, with the revenue each one brings in within the quarter. In the end all four collect the same total; what differs is when. Only when nobody decides is nothing finished this quarter.

Keep C first. This is today's plan, and for C it is the best one: it finishes in week five. The other two pay for that, and they pay three times what C gains. Can C go faster still? Not with engineering: it already has the whole team. The time left to buy sits inside the project, and we come to that below.

Push C back. A and B are finished this quarter, and C still brings in its money, only later. This is the best plan as long as nothing else wants those hours. A project that waits needs a date.

Take C out. A and B are finished this quarter as well. The company gives up what C would still have earned and gets the engineers' hours back. This plan wins as soon as those hours go to a project that earns more than C would. In an annual plan full of new proposals, that is rarely hard.

Whatever you decide about C, there is time to buy inside every project without touching the bottleneck, and Stephen Devaux's drag cost shows where. Figure 6 zooms in on A, the project with the highest price of a week. A's contract has that price both ways: a penalty for every week late, and a bonus for every week early, up to four weeks. Devaux calls that bonus the acceleration premium. A's engineering comes in two parts: first the long-lead items, so that the supplier can be ordered early, then the rest, which runs while the supplier delivers. Assembly and test follow. The critical path runs through the first part of the engineering, the supplier, assembly and test; the rest of the engineering has float. Every task on that path has drag, the weeks it adds to the finish date, and each of those weeks costs A its weekly price: that is the drag cost. Next to it stands what shortening the task costs per week. The supplier carries the most drag, and fast delivery costs less than half of what a week is worth. Two extra fitters on assembly buy another week for a quarter of its worth. Three weeks early, three weeks of bonus, for a third of that in extra cost, and not one engineering hour in it. The engineers' weeks are not for sale: if the bottleneck were easy to widen, it would not be the bottleneck. The fourth week of bonus sits there, and those hours belong to B and C as much as to A.

Inside project A: where a week can be bought. A's remaining plan, its critical path, what each task adds to the finish date (drag), and what it would cost to shorten it. A's contract pays a bonus of $20,000 for every week early, up to four weeks. Engineering of the long-lead items, 400 hours with the whole team, weeks 0 to 2: on the critical path, drag 2 weeks, drag cost $20,000 a week, cost to shorten: not for sale. Supplier delivers the long-lead parts, weeks 2 to 8: on the critical path, drag 3 weeks, drag cost $20,000 a week, cost to shorten $7,500 a week. Engineering, the rest, 600 hours, weeks 2 to 5 with three weeks of float: no drag, $0, nothing to gain. Assembly, weeks 8 to 10: drag 2 weeks, $20,000 a week, cost to shorten $5,000 a week. Test and handover, weeks 10 to 11: drag 1 week, $20,000 a week, no option to shorten. Delivery in week 11. Fast delivery (two weeks) and two extra fitters (one week): three weeks early for $20,000, a bonus of $60,000. The fourth week of bonus sits in the engineering, and those hours belong to B and C as much as to A. Buy time where the drag cost is highest, not from the bottleneck.

Figure 6. Inside project A: where a week of drag can be bought, and what it costs.

Does buying time in A help B and C? No. They do not wait for A's supplier or A's fitters; they wait for the engineers, and the engineers are released on the same day. The projects are staggered on the bottleneck. Each of them has its own critical path after the engineering, and that is where its weeks are bought. Before the bottleneck, speeding up buys nothing, and starting late even has a merit of its own: fewer requirements change while you wait.

Item 8 is the excuse that there is no way to stop a project. Then make one: agree on a limit in advance, so that nobody has to be the one who raises a project. For instance an RRI of one or less, or an hour of the bottleneck that earns less than a quarter of the portfolio average. C scrapes past the first and fails the second, so it comes up at the next review, and the rule is the same for every project. One reader described a portfolio of more than 300 projects, where a monthly review with the same questions for every project made stopping a normal outcome. Reviewed monthly, a project that drifts is a small decision. Left until the annual plan, it is a big one.

And yes, item 9, it is just hard to say no. The last number is the one that no report shows. If nobody decides, all three projects carry on together, each on a share of engineering, and all three finish late. Goldratt had a name for this as well: bad multitasking. Against the best plan, that costs the portfolio about $17,000 for every week the decision waits.

Not deciding is a decision as well. It is the only one of the four that nobody has to sign.

What to look at in your planning system: a what-if that recalculates every finish date and every amount when a project moves, waits or goes; the critical path of each project, with the drag and drag cost of every task on it; the limit itself, written down, and a fixed moment at which every project is held against it; and the gap in money between the plan you are running and the best plan you could run.

So when is a project cancellation the right decision?

In money, when the portfolio earns more without the project than with it. Not everything is money: a customer you want to keep, a market you want to be in, a team you want to hold together. Those weigh too, and you weigh them against a number instead of against a feeling. For C, the numbers say that it gives up its place. Whether C is stopped or waits at the back with a date depends on what else wants the hours. The numbers also say that spreading the team over everything, which is what happens when nobody decides, is the most expensive plan of the four.

Goldratt's five steps give the order. Find the bottleneck. Decide what its hours are for. Let every other decision follow that one. Only then add capacity. And when that changes where the bottleneck is, start again. Most annual plans jump to the fourth step and ask for more people. The nine numbers are the second step.

We have put everything in dollars here. It does not have to be money. A Formula 1 team weighs downforce, cornering speed and drivability, and the question stays the same: which piece of work brings the most of it for every hour of the people everything waits for?

How does Epicflow help?

With three projects and one engineering team, this is an afternoon with a spreadsheet. With forty projects and several teams that everybody waits for, every decision moves all the others. We built Epicflow as the instrument for that.

  • The bottleneck and the hours. Epicflow forecasts all projects at once on the real capacity of every team. You see which team each project waits for and how many hours it still needs.
  • The money. It shows the RRI of every project next to the ROI, and it puts a price on every date: a bonus or penalty per week, a payment per milestone.
  • The three decisions. Each one is a What-If next to your live plan: speed the project up, push it back or take it out. You see which finish dates move and what that does to the money. Nothing live changes until you decide.

For large portfolios, our AI searches millions of combinations for the set of projects and the order that earns the most. We run that for you as PMO as a Service. A spreadsheet is enough to begin: one row per resource group and one per project, with the six things from the questions at the end of this article, and we calculate the nine numbers for you.

Video. Three Mondays: every excuse has a price (90 seconds).

An instrument does not hold the answer for your business. Which of the nine numbers weighs most differs from one company to the next. Two of them depend on your own books and your own rules: which costs really stop, and where you set the limit. We are still learning there, with every portfolio we calculate.

Which number would you add?

These are our nine. One reader already offered a tenth excuse: some projects cannot be stopped because they pay for something else, out of sight. So there is probably a tenth number as well. Which one would you add, and what would you want to calculate for your own portfolio?

Annual planning season has started. See in two minutes what your plan leaves on the table.

Further reading: Stephen Devaux, who developed the method behind RRI, in The Managing-Projects-as-Investments Manifesto; on Flow Economics, How to Know When a Project Is No Longer Worth Finishing and the Price of Yes; and on this blog, Once in red, always in red and what portfolio rationalization is.

Frequently Asked Questions

When should you cancel a project?

When the whole portfolio earns more without it, after the cost of stopping has been counted, and never because of what has already been spent: that is sunk cost. Three numbers show it: what the project still returns for every dollar left to spend, what the same hours of the bottleneck earn in the other projects, and what the portfolio earns with the project kept first, pushed back or taken out.

What does it cost not to cancel a project?

In the example above, about $17,000 for every week the decision waits, and $150,000 in delay on two other projects if the project keeps its priority. Neither amount is in the business case or the budget of the project itself.

Is a project cancellation always better than a later date?

No. In the example, pushing the project back comes out ahead of stopping it, as long as nothing else wants the hours of the bottleneck. A project cancellation wins once a better project is waiting for those hours.

What project information do you need to take these decisions?

Six things per project, and nothing separate for the portfolio.

  • The revenue still to come, or a revenue scheme if it is recurring, per delivery milestone.
  • The target date.
  • The remaining hours per resource group.
  • The direct project cost still to come: materials, subcontractors.
  • The delay cost per week (penalties) and the acceleration premium (bonus), with any cap.
  • Per resource group, its capacity and its cost price, which give the operating expense.

Which resource group is the bottleneck, the finish dates and the nine numbers all follow from these. To see where a week can be bought, add a project file.

Can I send my project plan from Microsoft Project, Primavera or Monday.com?

Yes. To calculate drag and drag cost we need one project file per project with at least the task names, the links between tasks, the resource group of each task and the remaining work per task. The target date is already in the spreadsheet. Any format will do: Microsoft Project, Primavera P6, Excel, Monday.com, Smartsheet, Asana, Jira, Wrike, Planisware or a CSV export from any other tool.

What is the sunk cost fallacy in project management?

The belief that money already spent is a reason to carry on. In project management it comes dressed as "we have already spent so much on it" and "we are almost there". The spent money is gone whatever you decide, so the only question is what the project still brings in for what it still costs: the RRI. The bias is strongest in the people who championed the project, which is why the limit should be agreed in advance and the review should be the same for every project.

What are the criteria for terminating a project?

A limit agreed at approval raises the question; the portfolio answers it. The limit is a number, so that nobody has to be the one who raises a project: an RRI at or below one, or an hour of the bottleneck that earns less than a quarter of the portfolio average, checked at a fixed review every month. A project under the limit is a serious question, not yet a decision, because stopping saves less than the report says: the direct cost stops, the people stay on the payroll. If no better project is waiting for their hours, finishing a project with an RRI below one can still beat leaving them idle, as long as what it brings in exceeds the direct cost that stops. That is Goldratt's P and Q lesson, applied to projects. The usual warning signs, benefits no longer attainable, people and money drifting to other work, deliverables out of spec, are symptoms; the numbers say whether they matter.

How do you calculate the cost of delay for a project?

Give every project a price for a week later: the penalty in the contract, the revenue or recurring revenue that starts a week later, the bonus you no longer earn. The cost of delay is that price times the weeks. In the example a week costs A $20,000, B $10,000 and C $4,000. In a portfolio the delay is paid by the projects waiting behind the one that goes first, so the price of a week belongs to every project, not only to the one that shouts loudest.

Should you stop a project that is over budget?

Not because it is over budget. In the example, B ends up at twice its budget and still returns $5.00 for every dollar left to spend; stopping it would be the sunk cost fallacy the other way round. A project is stopped, or pushed back, when what it still brings in no longer beats what it still costs and what the same hours of the bottleneck earn elsewhere.

References

[1] Devaux, S. A. (1992). When the DIPP dips: A P&L index for project decisions. Project Management Journal, 23(3), 45-49. https://www.pmi.org/learning/library/economic-consideration-devaux-index-reject-performance-5343

About this article: The story, the example and the conclusions are my own, based on more than 25 years as an expert in this field and on my PhD research. Everything in it is based on real experience; the machine builder and its three projects are a simplified example, and its figures are illustrative. I used AI tools to help draft, edit and illustrate it, and I checked every fact and source myself. The voice in the video is an AI clone of my own voice.